IRON AND STEELWORKS

IRON AND STEELWORKS

Saarstahl Völklingen

2008-2010 Construction of a new forging facilities, „Forge Saar“ project – full system of distribution of industrial media (gas, steam, condensate, compressed air, oxygen, emulsions, heating, cooling, process water).

IRON AND STEELWORKS

Badische Stahlweke Kehl BSW

December 2009 - January 2010: Overhaul of pump stations and systems of cooling rolling mills 1 and 2 armatures.

IRON AND STEELWORKS

Dillinger Hüttenwerke – Blast Furnace No. 5 (HO5)

2006-2007: Production and assembling of ND2 cooling system with energy central station, pump stations, water cooling tower.

IRON AND STEELWORKS

ArcelorMittal Zenica

2011: Replacement of parts of feed pipeline of for dirty cycle of the PS-2 2011 pump station: Installation and examination of the system for water-run obturation of covers of gradient colons.